Flashline Station construction “well underway” Mars Society

Flashline Mars Arctic Research Station construction continues to proceed according to schedule. All habitat shell and structural elements are expected to be complete by April 14. The initial test assembly will begin April 15 – 17. If all goes well, the hab should be completely assembled by May 5. Interior systems installation will continue into May, with disassembly and shipment occurring in June. Planned completion of shell and structural assembly at Devon Island is July 20.